United States βΊ Grid βΊ Interconnection queues βΊ Nevada
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Nevada, CAISO
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Ashton Energy Center Solar + storage |
2,049 MW | Withdrawn / abandoned |
| Chance Solar Solar + storage |
1,790 MW | Withdrawn / abandoned |
| Searchlight 1 Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Sunvale Solar Farm Solar + storage |
1,200 MW | Withdrawn / abandoned |
| Amargosa SEZ Solar + storage |
1,019 MW | Withdrawn / abandoned |
| Coyote Springs Solar |
960 MW | Withdrawn / abandoned |
| White Oak Solar Solar + storage |
813 MW | Withdrawn / abandoned |
| Copper Rays Solar |
722 MW | Withdrawn / abandoned |
| Cathedral Solar + storage |
722 MW | Withdrawn / abandoned |
| Onyx Solar + storage |
706 MW | Withdrawn / abandoned |
| Copper Mountain II Gas |
634 MW | Withdrawn / abandoned |
| Copper Mountain II Alternate Gas |
634 MW | Withdrawn / abandoned |
| Copper Mountain Project Gas |
634 MW | Withdrawn / abandoned |
| Bullhead Solar Solar + storage |
600 MW | Withdrawn / abandoned |
| El Dorado Valley Generation Gas |
600 MW | Withdrawn / abandoned |
| Bighorn Gas |
591 MW | Withdrawn / abandoned |
| Reliant Energy Bighorn Gas |
591 MW | Withdrawn / abandoned |
| Sloan Energy Center Solar + storage |
578 MW | Withdrawn / abandoned |
| Reed Meadow Battery storage |
566 MW | Withdrawn / abandoned |
| Hidden Hills Ranch Solar |
540 MW | Withdrawn / abandoned |
| Sandy Valley Phase II Segs Gas |
540 MW | Withdrawn / abandoned |
| Alum Geothermal Geothermal |
530 MW | Withdrawn / abandoned |
| Grapevine 2 Battery storage |
505 MW | Withdrawn / abandoned |
| Bonanza Solar 2 Solar + storage |
450 MW | Withdrawn / abandoned |
| Jean Lake Solar Solar |
400 MW | Withdrawn / abandoned |
| Panoche Valley Solar Farm Expansion Solar |
400 MW | Withdrawn / abandoned |
| Nevada Mohave Solar Solar |
400 MW | Withdrawn / abandoned |
| Southland Solar |
380 MW | Withdrawn / abandoned |
| TGP NNP Geothermal |
364 MW | Withdrawn / abandoned |
| Hiko Battery storage |
360 MW | Withdrawn / abandoned |
| Nevada 300 Solar |
300 MW | Withdrawn / abandoned |
| Enn Mojave Power 4 Other |
300 MW | Withdrawn / abandoned |
| Enn Mojave Power 3 Other |
300 MW | Withdrawn / abandoned |
| Boulder Solar Power Solar |
300 MW | Withdrawn / abandoned |
| Copper MTN Solar 5 Solar + storage |
277 MW | Withdrawn / abandoned |
| Sandy Valley Phase I Segs (Fka Pahrump Valley Segs) Solar |
270 MW | Withdrawn / abandoned |
| Boulder Solar 3 (Fka: Boulder Solar Power C7) Solar |
250 MW | Withdrawn / abandoned |
| Campos Solar Energy Solar |
250 MW | Withdrawn / abandoned |
| Sandy Valley Solar Project Solar |
250 MW | Withdrawn / abandoned |
| Enn Mojave Power 1 Other |
250 MW | Withdrawn / abandoned |
| Enn Mojave Power 2 Other |
250 MW | Withdrawn / abandoned |
| Copper Mountain Solar III (Black Hills) Solar |
242 MW | Withdrawn / abandoned |
| Mccullough Pass Solar Project Solar |
240 MW | Withdrawn / abandoned |
| Pahrump Valley Solar (Fka Lathrop Wells 240MW) Solar |
210 MW | Withdrawn / abandoned |
| Re Prism Solar |
209 MW | Withdrawn / abandoned |
| South Ridge Solar |
205 MW | Withdrawn / abandoned |
| Pearl Geothermal Geothermal |
200 MW | Withdrawn / abandoned |
| Copper Rays Solar Solar |
180 MW | Withdrawn / abandoned |
| Townsite Solar Project Solar |
180 MW | Withdrawn / abandoned |
| Black Hills Playa B Solar Solar + storage |
154 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)