United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Nevada, CAISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8328.8 GW
Active in queue16.7 GW31 requests
Agreement signed8,618 MW16 requests
Withdrawn8328.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

83 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Ashton Energy Center
Solar + storage
2,049 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2032
Chance Solar
Solar + storage
1,790 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2028
Searchlight 1
Onshore wind
1,500 MWWithdrawn / abandoned Clark, NVCAISO Aug 2006target 2011
Sunvale Solar Farm
Solar + storage
1,200 MWWithdrawn / abandoned Clark, NVCAISO Apr 2018target 2022
Amargosa SEZ
Solar + storage
1,019 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2030
Coyote Springs
Solar
960 MWWithdrawn / abandoned Lincoln, NVCAISO Jul 2009target 2015
White Oak Solar
Solar + storage
813 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2029
Copper Rays
Solar
722 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2021
Cathedral
Solar + storage
722 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2031
Onyx
Solar + storage
706 MWWithdrawn / abandoned Clark, NVCAISO Apr 2023target 2030
Copper Mountain II
Gas
634 MWWithdrawn / abandoned Clark, NVCAISO Jul 2007target 2011
Copper Mountain II Alternate
Gas
634 MWWithdrawn / abandoned Clark, NVCAISO Oct 2007target 2011
Copper Mountain Project
Gas
634 MWWithdrawn / abandoned Clark, NVCAISO Jan 2005target 2009
Bullhead Solar
Solar + storage
600 MWWithdrawn / abandoned Clark, NVCAISO Apr 2019target 2023
El Dorado Valley Generation
Gas
600 MWWithdrawn / abandoned Clark, NVCAISO Feb 2010target 2014
Bighorn
Gas
591 MWWithdrawn / abandoned Clark, NVCAISO Nov 2006target 2010
Reliant Energy Bighorn
Gas
591 MWWithdrawn / abandoned Clark, NVCAISO Jun 2005target 2007
Sloan Energy Center
Solar + storage
578 MWWithdrawn / abandoned Clark, NVCAISO Apr 2019target 2023
Reed Meadow
Battery storage
566 MWWithdrawn / abandoned Clark, NVCAISO Apr 2023target 2031
Hidden Hills Ranch
Solar
540 MWWithdrawn / abandoned Nye, NVCAISO Mar 2011target 2014
Sandy Valley Phase II Segs
Gas
540 MWWithdrawn / abandoned Clark, NVCAISO Apr 2012target 2016
Alum Geothermal
Geothermal
530 MWWithdrawn / abandoned Esmeralda, NVCAISO Apr 2021target 2025
Grapevine 2
Battery storage
505 MWWithdrawn / abandoned Clark, NVCAISO Apr 2023target 2028
Bonanza Solar 2
Solar + storage
450 MWWithdrawn / abandoned Clark, NVCAISO Apr 2020target 2024
Jean Lake Solar
Solar
400 MWWithdrawn / abandoned Clark, NVCAISO Jun 2007target 2013
Panoche Valley Solar Farm Expansion
Solar
400 MWWithdrawn / abandoned San Benito, NVCAISO Feb 2010target 2013
Nevada Mohave Solar
Solar
400 MWWithdrawn / abandoned Clark, NVCAISO Apr 2015target 2024
Southland
Solar
380 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2023
TGP NNP
Geothermal
364 MWWithdrawn / abandoned Churchill, NVCAISO Jul 2010target 2016
Hiko
Battery storage
360 MWWithdrawn / abandoned Clark, NVCAISO Apr 2023target 2031
Nevada 300
Solar
300 MWWithdrawn / abandoned Clark, NVCAISO Jul 2010target 2014
Enn Mojave Power 4
Other
300 MWWithdrawn / abandoned Clark, NVCAISO Apr 2012target 2016
Enn Mojave Power 3
Other
300 MWWithdrawn / abandoned Clark, NVCAISO Apr 2012target 2016
Boulder Solar Power
Solar
300 MWWithdrawn / abandoned Clark, NVCAISO Apr 2012target 2016
Copper MTN Solar 5
Solar + storage
277 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2023
Sandy Valley Phase I Segs (Fka Pahrump Valley Segs)
Solar
270 MWWithdrawn / abandoned Clark, NVCAISO Mar 2011target 2016
Boulder Solar 3 (Fka: Boulder Solar Power C7)
Solar
250 MWWithdrawn / abandoned Clark, NVCAISO Apr 2014target 2018
Campos Solar Energy
Solar
250 MWWithdrawn / abandoned Clark, NVCAISO May 2008target 2014
Sandy Valley Solar Project
Solar
250 MWWithdrawn / abandoned Nye, NVCAISO Apr 2012target 2018
Enn Mojave Power 1
Other
250 MWWithdrawn / abandoned Clark, NVCAISO Apr 2012target 2016
Enn Mojave Power 2
Other
250 MWWithdrawn / abandoned Clark, NVCAISO Apr 2012target 2016
Copper Mountain Solar III (Black Hills)
Solar
242 MWWithdrawn / abandoned Clark, NVCAISO Jul 2010target 2013
Mccullough Pass Solar Project
Solar
240 MWWithdrawn / abandoned Clark, NVCAISO May 2008target 2013
Pahrump Valley Solar (Fka Lathrop Wells 240MW)
Solar
210 MWWithdrawn / abandoned Nye, NVCAISO Apr 2012target 2019
Re Prism
Solar
209 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2019
South Ridge
Solar
205 MWWithdrawn / abandoned Nye, NVCAISO May 2016target 2021
Pearl Geothermal
Geothermal
200 MWWithdrawn / abandoned Esmeralda, NVCAISO Apr 2021target 2027
Copper Rays Solar
Solar
180 MWWithdrawn / abandoned Nye, NVCAISO Apr 2012target 2013
Townsite Solar Project
Solar
180 MWWithdrawn / abandoned Clark, NVCAISO Apr 2012target 2016
Black Hills Playa B Solar
Solar + storage
154 MWWithdrawn / abandoned Clark, NVCAISO Apr 2019target 2023
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)