SOLAR Β· CAISO

Coyote Springs

Coyote Springs is a 960 MW solar request withdrawn in the CAISO interconnection queue, in Lincoln County, Nevada, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2009 (completed)
  2. Withdrawn / abandonedMar 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
500
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Eldorado Substation 500kV
Location
Lincoln County, Nevada
Technology
Solar: 960 MW
Total requested
960 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 July 2009
Proposed online date
January 2015
Withdrawn
March 2011

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem