SOLAR Β· WEST

Solar project Company 90, Lincoln County

Solar project Company 90, Lincoln County is a 100 MW solar request withdrawn in the West interconnection queue, in Lincoln County, Nevada, connecting to NV Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2010 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Company 90
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Lincoln County, Nevada
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
23 March 2010
Proposed online date
October 2012

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem