United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

SOLAR Β· CAISO

Nevada 300

Nevada 300 is a 300 MW solar request withdrawn in the CAISO interconnection queue, in Clark County, Nevada, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2010 (completed)
  2. Withdrawn / abandonedMay 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
643AI
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Eldorado Sub 220 kV Bus
Location
Clark County, Nevada
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 July 2010
Proposed online date
November 2014
Withdrawn
May 2013

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem