United States βΊ Grid βΊ Interconnection queues βΊ Nevada
GEOTHERMAL Β· CAISOPearl Geothermal
Pearl Geothermal is a 200 MW geothermal request withdrawn in the CAISO interconnection queue, in Esmeralda County, Nevada, connecting to SCE.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2021 (completed)
- Withdrawn / abandonedJan 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 2106
- Grid region
- CAISO (California)
- Utility / transmission owner
- SCE
- Connection point (POI)
- Control Substation 115 kV
- Location
- Esmeralda County, Nevada
- Technology
- Geothermal: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 15 April 2021
- Proposed online date
- September 2027
- Withdrawn
- January 2023
Location
Marker shows the centre of Esmeralda County; the queue data does not give exact sites.
Other requests in Esmeralda County
- Geothermal project Company KH, Esmeralda CountyGeothermal Β· 38.5 MW Β· agreement signed
- Geothermal project Company KY, Esmeralda CountyGeothermal Β· 38.5 MW Β· agreement signed
- Geothermal project Company MM, Esmeralda CountyGeothermal Β· 19.8 MW Β· agreement signed
- Solar + storage project 25-00394, Esmerelda CountySolar + storage Β· 1,000 MW Β· in study
- Solar + storage project Company PK, Esmeralda CountySolar + storage Β· 500 MW Β· in study
- Solar + storage project Company OI, Esmeralda CountySolar + storage Β· 380 MW Β· in study
- Solar + storage project Company PR, Esmeralda CountySolar + storage Β· 300 MW Β· in study
- Solar + storage project Company OJ, Esmeralda CountySolar + storage Β· 200 MW Β· in study
- Solar + storage project Company PQ, Esmeralda CountySolar + storage Β· 200 MW Β· in study
- Solar + storage project Company PM, Esmeralda CountySolar + storage Β· 1,500 MW Β· withdrawn
- Solar + storage project Company OZ, Esmeralda CountySolar + storage Β· 1,000 MW Β· withdrawn
- Solar + storage project Company PB, Esmeralda CountySolar + storage Β· 1,000 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem