Geothermal project Company MM, Esmeralda County

Geothermal project Company MM, Esmeralda County is a 19.8 MW geothermal request with a signed interconnection agreement in the West interconnection queue, in Esmeralda County, Nevada, connecting to NV Energy.

Queue statusConsented
  1. PlanningQueued Dec 2021 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
Company MM
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Esmeralda County, Nevada
Technology
Geothermal: 19.8 MW
Total requested
19.8 MW
Service type
NRIS and ERIS
Study phase
IA Executed
Queue status
Active
Entered queue
8 December 2021
Proposed online date
October 2025

Location

Marker shows the centre of Esmeralda County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Esmeralda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem