WIND + STORAGE Β· WEST

Wind + storage project Company QI, Esmeralda County

Wind + storage project Company QI, Esmeralda County is a 960 MW wind + storage request withdrawn in the West interconnection queue, in Esmeralda County, Nevada, connecting to NV Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Company QI
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Esmeralda County, Nevada
Technology
Wind: 960 MW Β· Battery
Total requested
960 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
25 September 2023
Proposed online date
December 2027

Location

Marker shows the centre of Esmeralda County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Esmeralda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem