🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nevada

SOLAR · CAISO

Mccullough Pass Solar Project

Mccullough Pass Solar Project is a 240 MW solar request withdrawn in the CAISO interconnection queue, in Clark County, Nevada, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2008 (completed)
  2. Withdrawn / abandonedDec 2009 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
381
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Eldorado Subsation 230kV
Location
Clark County, Nevada
Technology
Solar: 240 MW
Total requested
240 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
29 May 2008
Proposed online date
May 2013
Withdrawn
December 2009

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem