Jean Lake Solar

Jean Lake Solar is a 400 MW solar request withdrawn in the CAISO interconnection queue, in Clark County, Nevada, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2007 (completed)
  2. Withdrawn / abandonedApr 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
234
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Proposed Eldorado-Ivanpah 230kV line
Location
Clark County, Nevada
Technology
Solar: 400 MW
Total requested
400 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
27 June 2007
Proposed online date
June 2013
Withdrawn
April 2011

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Clark County