United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

ONSHORE WIND Β· CAISO

Searchlight 1

Searchlight 1 is a 1,500 MW onshore wind request withdrawn in the CAISO interconnection queue, in Clark County, Nevada, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2006 (completed)
  2. Withdrawn / abandonedJun 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
126
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Eldorado Substation 220kV bus
Location
Clark County, Nevada
Technology
Wind: 1,500 MW
Total requested
1,500 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 August 2006
Proposed online date
December 2011
Withdrawn
June 2012

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Nevada Β· Transmission lines in Nevada

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem