United States βΊ Grid βΊ Interconnection queues βΊ Nevada
SOLAR + STORAGE Β· CAISOWhite Oak Solar
White Oak Solar is a 813 MW solar + storage request withdrawn in the CAISO interconnection queue, in Nye County, Nevada, connecting to GLW.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2023 (completed)
- Withdrawn / abandonedMay 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 2271
- Grid region
- CAISO (California)
- Utility / transmission owner
- GLW
- Connection point (POI)
- VALLEY SWITCH 230 kV
- Location
- Nye County, Nevada
- Technology
- Solar: 407 MW Β· Battery: 406 MW
- Total requested
- 813 MW
- Service type
- Energy only (ERIS)
- Study phase
- Caiso Cluster 15 Unvalidated
- Queue status
- Withdrawn
- Entered queue
- 17 April 2023
- Proposed online date
- December 2029
- Withdrawn
- May 2025
Location
Marker shows the centre of Nye County; the queue data does not give exact sites.
Other requests in Nye County
- Silver Star SolarSolar + storage Β· 1,034 MW Β· agreement signed
- Rock Valley Energy CenterSolar + storage Β· 1,024 MW Β· agreement signed
- Rough Hat Hybrid SolarSolar + storage Β· 404 MW Β· agreement signed
- Water Rock Solar 1Solar + storage Β· 400 MW Β· agreement signed
- Sunshine Valley Solar 1Solar + storage Β· 90.0 MW Β· agreement signed
- Ares NevadaBattery storage Β· 44.0 MW Β· agreement signed
- Water Rock Solar 2Solar + storage Β· 1,034 MW Β· in study
- Solar + storage project Company 238, Nye CountySolar + storage Β· 1,000 MW Β· in study
- BristleconeSolar + storage Β· 921 MW Β· in study
- Solar + storage project Company 254, Nye CountySolar + storage Β· 600 MW Β· in study
- Solar + storage project Company 255, Nye CountySolar + storage Β· 600 MW Β· in study
- Solar + storage project Company 256, Nye CountySolar + storage Β· 500 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem