United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Onshore wind interconnection queue in the USA — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown826200.1 GW
Active in queue200.1 GW826 requests
Agreement signed49.9 GW242 requests
Withdrawn4,524860.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

826 requests · page 8 of 17
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2024-236, Okfuskee County
Onshore wind
241 MWIn study Okfuskee, OKSPP Mar 2025target 2029
Peyton Creek Wind II
Onshore wind · RWE Renewables Development, LLC
241 MWAgreement signed Matagorda, TXERCOT Aug 2018target 2026
Giddings Wind
Onshore wind · Pioneer Natural Resources
240 MWIn study Upton, TXERCOT Sep 2017target 2030
Bob Creek Wind
Onshore wind · NextEra Energy Interconnection Holdings, LLC
240 MWAgreement signed Sterling, TXERCOT Jan 2024target 2028
Onshore wind project G0640, Klamath County
Onshore wind
239 MWIn study Klamath, ORWest Feb 2020target 2025
Campsey Wind
Onshore wind · RWE Clean Energy Development, LLC
238 MWIn study Jack, TXERCOT Feb 2021target 2028
Onshore wind project G0435, Morrow County
Onshore wind
238 MWIn study Morrow, ORWest Aug 2010target 2013
Onshore wind project GI-53, Nodaway County
Onshore wind
238 MWAgreement signed Nodaway, MOSoutheast May 2016target 2018
Onshore wind project GI-2004-2, Baca County
Onshore wind
238 MWAgreement signed Baca, COWest Feb 2004
Onshore wind project J3856, Wabash County
Onshore wind
235 MWIn study Wabash, ILMISO Dec 2024target 2030
Monte Cristo 1 Wind
Onshore wind · Terra-Gen
235 MWAgreement signed Hidalgo, TXERCOT Apr 2017target 2025
Onshore wind project G1036, Hood River County
Onshore wind
234 MWIn study Hood River, ORWest Nov 2023target 2028
Monte Cristo II Wind
Onshore wind · Monte Cristo Windpower II, LLC
234 MWAgreement signed Hidalgo, TXERCOT Apr 2017target 2028
Onshore wind project G0683, Benton County
Onshore wind
233 MWIn study Benton, WAWest Jul 2021target 2026
Onshore wind project J4068, Marshall County
Onshore wind
232 MWIn study Marshall, IAMISO Oct 2025target 2030
Buffalo Gap 2 Wind Repower
Onshore wind · Buffalo Gap Wind Farm 2, LLC
232 MWAgreement signed Nolan, TXERCOT Dec 2024target 2026
Onshore wind project GEN-2018-125, Lancaster County
Onshore wind
231 MWAgreement signed Lancaster, NESPP Nov 2018target 2031
Onshore wind project GI-61, Nodaway County
Onshore wind
230 MWAgreement signed Nodaway, MOSoutheast May 2017target 2019
Onshore wind project J2104, Murray County
Onshore wind
230 MWIn study Murray, MNMISO Sep 2025target 2024
Onshore wind project GEN-2023-229, Caddo County
Onshore wind
230 MWIn study Caddo, OKSPP Oct 2023target 2029
Onshore wind project J2342, Worth County
Onshore wind
230 MWIn study Worth, IAMISO Sep 2022target 2027
Onshore wind project J3864, Shiawassee County
Onshore wind
230 MWIn study Shiawassee, MIMISO Dec 2024target 2028
Rubicon Echo Wind
Onshore wind
228 MWPaused / redesign Haskell, TXERCOT May 2022
Gulf Wind 2
Onshore wind
227 MWPaused / redesign Kenedy, TXERCOT Jan 2018
Rubicon Alpha Wind
Onshore wind · Throckmorton Wind, LLC
226 MWAgreement signed Haskell, TXERCOT May 2022target 2027
Aquilla Lake 3 Wind (Alternative POI Oncor 138KV)
Onshore wind
226 MWPaused / redesign Hill, TXERCOT Aug 2023target 2026
Aquilla Lake 3 Wind ( Alternative POI Oncor 345kV)
Onshore wind
226 MWPaused / redesign Hill, TXERCOT Sep 2023target 2026
Onshore wind project J3830
Onshore wind
225 MWIn study ILMISO Apr 2024target 2028
Onshore wind project GEN-2024-216, Custer County
Onshore wind
225 MWIn study Custer, MTSPP Mar 2025target 2027
Onshore wind project GI-CS-2025-24, Kit Carson County
Onshore wind
225 MWIn study Kit Carson, COWest Sep 2025target 2029
Onshore wind project CS23-06, Whitman County
Onshore wind
221 MWAgreement signed Whitman, WAWest Apr 2023target 2028
Onshore wind project GEN-2015-066, Pawnee County
Onshore wind
220 MWAgreement signed Pawnee, OKSPP Oct 20152025
Onshore wind project J3496, Sanilac County
Onshore wind
220 MWIn study Sanilac, MIMISO Apr 2024target 2027
Onshore wind project GEN-2024-346, Nowata County
Onshore wind
220 MWIn study Nowata, OKSPP Mar 2025target 2030
Onshore wind project GEN-2017-233, Grady County
Onshore wind
215 MWAgreement signed Grady, OKSPP Nov 2017target 2027
Onshore wind project GEN-2022-176, Nowata County
Onshore wind
215 MWIn study Nowata, OKSPP Feb 2023target 2028
Onshore wind project GEN-2018-082, Pittsburg County
Onshore wind
215 MWAgreement signed Pittsburg, OKSPP Nov 2018target 2030
Mesquite Creek Windpower Repower
Onshore wind · Mesquite Creek Wind LLC
213 MWIn study Dawson, TXERCOT Apr 2025target 2027
Gusty Windpower
Onshore wind · Gusty Windpower, LLC
209 MWAgreement signed Glasscock, TXERCOT Jul 2024target 2028
Fountain Wind
Onshore wind
206 MWAgreement signed Shasta, CACAISO Apr 2015target 2027
Onshore wind project C2-92, Bingham County
Onshore wind · PacifiCorp
206 MWIn study Bingham, IDWest May 2022target 2026
Onshore wind project MPC04400, Grand Forks County
Onshore wind
206 MWIn study Grand Forks, NDMISO Feb 2022target 2024
Supra Wind
Onshore wind · NextEra Energy Interconnection Holdings, LLC
206 MWIn study Hardeman, TXERCOT Jul 2023target 2027
Onshore wind project G0362, Gilliam County
Onshore wind
204 MWIn study Gilliam, ORWest Apr 2009target 2012
Onshore wind project G0363, Gilliam County
Onshore wind
204 MWIn study Gilliam, ORWest Apr 2009target 2012
Onshore wind project GEN-2021-025, Woodward County
Onshore wind
203 MWIn study Woodward, OKSPP May 2021target 2026
Guajillo Wind
Onshore wind · Guajillo Wind LLC
202 MWIn study Duval, TXERCOT Dec 2024target 2028
Willow Beach Wind
Onshore wind · Capital Wind, LLC
202 MWAgreement signed Brazoria, TXERCOT Oct 2023target 2027
Onshore wind project GEN-2016-004, Oliver County
Onshore wind
202 MWAgreement signed Oliver, NDSPP Mar 2016target 2027
Onshore wind project GEN-2017-004, Cloud County
Onshore wind
202 MWAgreement signed Cloud, KSSPP Apr 2017target 2027
Page 8 of 17

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)