United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTBuffalo Gap 2 Wind Repower
Buffalo Gap 2 Wind Repower is a 232 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Nolan County, Texas.
Queue statusConsented
- PlanningQueued Dec 2024 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 26INR0625
- Grid region
- ERCOT (Texas)
- Developer
- Buffalo Gap Wind Farm 2, LLC
- Connection point (POI)
- 6216 Bluff Creek 138 kV
- Location
- Nolan County, Texas
- Technology
- Wind: 232 MW
- Total requested
- 232 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 19 December 2024
- Proposed online date
- December 2026
Location
Marker shows the centre of Nolan County; the queue data does not give exact sites.
Other requests in Nolan County
- Maryneal WindOnshore wind · 182 MW · agreement signed
- Buffalo Gap 1 Wind RepowerOnshore wind · 120 MW · agreement signed
- Sweetwater 2 repowerOnshore wind · 7.3 MW · agreement signed
- Trent repowerOnshore wind · 6.4 MW · agreement signed
- Sweetwater 1 repowerOnshore wind · 3.0 MW · agreement signed
- Champion Wind RepowerOnshore wind · 0.3 MW · agreement signed
- Harley Hand SolarSolar + storage · 506 MW · in study
- Harley Hand StorageSolar + storage · 503 MW · in study
- Themisto SolarSolar · 301 MW · in study
- Sepanta SolarSolar · 217 MW · in study
- Sagebrush WindOnshore wind · 200 MW · in study
- Jaguarundi Energy StorageBattery storage · 152 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem