United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTChampion Wind Repower
Champion Wind Repower is a 0.3 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Nolan County, Texas.
Queue statusConsented
- PlanningQueued Sep 2023 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget May 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 24INR0627
- Grid region
- ERCOT (Texas)
- Developer
- Champion Wind Farm, LLC
- Connection point (POI)
- Bus# 1048 - Tonkawa
- Location
- Nolan County, Texas
- Technology
- Wind: 0.3 MW
- Total requested
- 0.3 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 25 September 2023
- Proposed online date
- May 2025
Location
Marker shows the centre of Nolan County; the queue data does not give exact sites.
Other requests in Nolan County
- Buffalo Gap 2 Wind RepowerOnshore wind · 232 MW · agreement signed
- Maryneal WindOnshore wind · 182 MW · agreement signed
- Buffalo Gap 1 Wind RepowerOnshore wind · 120 MW · agreement signed
- Sweetwater 2 repowerOnshore wind · 7.3 MW · agreement signed
- Trent repowerOnshore wind · 6.4 MW · agreement signed
- Sweetwater 1 repowerOnshore wind · 3.0 MW · agreement signed
- Harley Hand SolarSolar + storage · 506 MW · in study
- Harley Hand StorageSolar + storage · 503 MW · in study
- Themisto SolarSolar · 301 MW · in study
- Sepanta SolarSolar · 217 MW · in study
- Sagebrush WindOnshore wind · 200 MW · in study
- Jaguarundi Energy StorageBattery storage · 152 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem