United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTTrent repower
Trent repower is a 6.4 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Nolan County, Texas.
Queue statusConsented
- PlanningQueued Nov 2017 (completed)
- ConsentedOct 2018 (current stage)
- Construction (not yet reached)
- OperatingTarget Jan 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 17INR0069
- Grid region
- ERCOT (Texas)
- Developer
- TRENT WIND FARM LLC
- Connection point (POI)
- 1338 Eskota 138kV
- Location
- Nolan County, Texas
- Technology
- Wind: 6.4 MW
- Total requested
- 6.4 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 8 November 2017
- Agreement signed
- 19 October 2018
- Proposed online date
- January 2026
Location
Marker shows the centre of Nolan County; the queue data does not give exact sites.
Other requests in Nolan County
- Buffalo Gap 2 Wind RepowerOnshore wind · 232 MW · agreement signed
- Maryneal WindOnshore wind · 182 MW · agreement signed
- Buffalo Gap 1 Wind RepowerOnshore wind · 120 MW · agreement signed
- Sweetwater 2 repowerOnshore wind · 7.3 MW · agreement signed
- Sweetwater 1 repowerOnshore wind · 3.0 MW · agreement signed
- Champion Wind RepowerOnshore wind · 0.3 MW · agreement signed
- Harley Hand SolarSolar + storage · 506 MW · in study
- Harley Hand StorageSolar + storage · 503 MW · in study
- Themisto SolarSolar · 301 MW · in study
- Sepanta SolarSolar · 217 MW · in study
- Sagebrush WindOnshore wind · 200 MW · in study
- Jaguarundi Energy StorageBattery storage · 152 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem