United States › Grid › Interconnection queues › Oklahoma

ONSHORE WIND · SPP

Onshore wind project GEN-2015-066, Pawnee County

Onshore wind project GEN-2015-066, Pawnee County is a 220 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Pawnee County, Oklahoma, connecting to OGE.

Queue statusConsented
  1. PlanningQueued Oct 2015 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingDec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2015-066
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Sooner - Cleveland 345kV
Location
Pawnee County, Oklahoma
Technology
Wind: 220 MW
Total requested
220 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
7 October 2015
Proposed online date
December 2025
Came online
December 2025

Location

Marker shows the centre of Pawnee County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Pawnee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem