United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
ONSHORE WIND Β· SPPOnshore wind project GEN-2008-057, Pawnee County
Onshore wind project GEN-2008-057, Pawnee County is a 260 MW onshore wind request withdrawn in the SPP interconnection queue, in Pawnee County, Oklahoma, connecting to GRDA.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2008 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2008-057
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- GRDA
- Location
- Pawnee County, Oklahoma
- Technology
- Wind: 260 MW
- Total requested
- 260 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 9 June 2008
- Proposed online date
- December 2011
Location
Marker shows the centre of Pawnee County; the queue data does not give exact sites.
Other requests in Pawnee County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem