ONSHORE WIND · CAISOFountain Wind
Fountain Wind is a 206 MW onshore wind request with a signed interconnection agreement in the CAISO interconnection queue, in Shasta County, California, connecting to PGAE.
Queue statusConsented
- PlanningQueued Apr 2015 (completed)
- ConsentedNov 2017 (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1106
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Pit 1-Cottonwood 230 kV Line
- Location
- Shasta County, California
- Technology
- Wind: 206 MW
- Total requested
- 206 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 30 April 2015
- Agreement signed
- 29 November 2017
- Proposed online date
- September 2027
Location
Marker shows the centre of Shasta County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Shasta County
- Solar + storage project 2024-G2, Shasta CountySolar + storage · 125 MW · in study
- Hatchet Ridge Wind Farm ProjectOnshore wind · 102 MW · built
- Hydro project 1055, Shasta CountyHydro · 4.2 MW · built
- Round Mountain Wind ProjectOnshore wind · 350 MW · withdrawn
- Crossroads StorageBattery storage · 313 MW · withdrawn
- Timber Hills Wind (Fka Hillcrest Wind Power 1)Onshore wind · 138 MW · withdrawn
- Meadow Ridge Solar And BatterySolar + storage · 114 MW · withdrawn
- Las Hermanas BESSBattery storage · 110 MW · withdrawn
- Paradise Peak Wind Power ProjectOnshore wind · 102 MW · withdrawn
- Origin Energy StorageBattery storage · 102 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem