BATTERY STORAGE · CAISOLas Hermanas BESS
Las Hermanas BESS is a 110 MW battery storage request withdrawn in the CAISO interconnection queue, in Shasta County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2016 (completed)
- Withdrawn / abandonedJul 2016 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1276
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Carberry Switching Station 230kV
- Location
- Shasta County, California
- Technology
- Battery: 110 MW
- Total requested
- 110 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 2 May 2016
- Proposed online date
- May 2019
- Withdrawn
- July 2016
Location
Marker shows the centre of Shasta County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Shasta County
- Fountain WindOnshore wind · 206 MW · agreement signed
- Solar + storage project 2024-G2, Shasta CountySolar + storage · 125 MW · in study
- Hatchet Ridge Wind Farm ProjectOnshore wind · 102 MW · built
- Hydro project 1055, Shasta CountyHydro · 4.2 MW · built
- Round Mountain Wind ProjectOnshore wind · 350 MW · withdrawn
- Crossroads StorageBattery storage · 313 MW · withdrawn
- Timber Hills Wind (Fka Hillcrest Wind Power 1)Onshore wind · 138 MW · withdrawn
- Meadow Ridge Solar And BatterySolar + storage · 114 MW · withdrawn
- Paradise Peak Wind Power ProjectOnshore wind · 102 MW · withdrawn
- Origin Energy StorageBattery storage · 102 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem