🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Washington

ONSHORE WIND · WEST

Onshore wind project CS23-06, Whitman County

Onshore wind project CS23-06, Whitman County is a 221 MW onshore wind request with a signed interconnection agreement in the West interconnection queue, in Whitman County, Washington, connecting to Avista Utilities.

Queue statusConsented
  1. PlanningQueued Apr 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
CS23-06
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Shawnee - Thornton 230kV
Location
Whitman County, Washington
Technology
Wind: 221 MW
Total requested
221 MW
Service type
NRIS and ERIS
Study phase
Request Status: LGIA; Facilities Study: Complete; Phase One Cluster Study: Complete; Phase One Re-Study: N/A; Phase Two
Queue status
Active
Entered queue
14 April 2023
Proposed online date
September 2028

Location

Marker shows the centre of Whitman County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Whitman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem