🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas (2025 requests) — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown402116.3 GW
Active in queue116.3 GW402 requests
Agreement signed4,428 MW22 requests
Withdrawn164,201 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

402 requests · page 8 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Strawberry Dunes Solar SLF
Solar + storage · Strawberry Dunes LLC
101 MWIn study Atascosa, TXERCOT Feb 2025target 2028
Calf Creek Storage
Battery storage · Coyote Ridge Storage, LLC
101 MWIn study Howard, TXERCOT Nov 2025target 2028
Goat Mountain BESS 2
Wind + storage · Goat Wind LLC
101 MWIn study Sterling, TXERCOT Jan 2025target 2027
Mobee Springs BESS
Battery storage · Mobee Springs, LLC
101 MWIn study Refugio, TXERCOT Jun 2025target 2028
Firefly Fields Solar
Solar + storage · Firefly Fields Energy Center LLC
101 MWIn study Colorado, TXERCOT Jan 2025target 2028
Diamond Sage BESS 2
Solar + storage · DGC Renewables, LLC
100 MWIn study Webb, TXERCOT Jan 2025target 2028
Diamond Sage BESS 1
Solar + storage · DGC Renewables, LLC
100 MWIn study Webb, TXERCOT Jan 2025target 2028
Erika BESS
Solar + storage · Erika Solar, LLC
100 MWIn study Kaufman, TXERCOT Jun 2025target 2029
Solar project J4124, Trinity County
Solar
100 MWIn study Trinity, TXMISO Aug 2025target 2029
Radiant Plains Energy Center Solar
Solar + storage · Adapture Solar Development
100 MWIn study Colorado, TXERCOT Jun 2025target 2029
Solar project GEN-2024-241, Bowie County
Solar
100 MWIn study Bowie, TXSPP Mar 2025target 2028
Radiant Plains Energy Center BESS
Solar + storage · Adapture Solar Development
100 MWIn study Colorado, TXERCOT Jun 2025target 2029
Timmerman Power Plant Phase 2B
Gas · Lower Colorado River Authority
94.2 MWAgreement signed Caldwell, TXERCOT Oct 2025target 2026
Rattlesnake Gap Solar SLF
Solar + storage · ET Fuels US Inc.
93.0 MWIn study Howard, TXERCOT Sep 2025target 2029
Bandana Solar SLF
Solar
86.9 MWPaused / redesign Jim Wells, TXERCOT Apr 2025
Galaxy I Solar
Solar + storage · Galaxy Solar, LLC
82.9 MWIn study Ellis, TXERCOT Apr 2025target 2028
Soluce Bravo Solar
Solar + storage · BNPB1, LLC
80.5 MWIn study Brown, TXERCOT Jan 2025target 2028
Lytton Springs BESS
Solar + storage · SMT Lytton Springs LLC
76.4 MWIn study Caldwell, TXERCOT Dec 2025target 2027
Donelson Solar SLF
Solar + storage · Donelson Solar
75.4 MWIn study Red River, TXERCOT Mar 2025target 2028
Lytton Springs Solar
Solar + storage · SMT Lytton Springs LLC
75.3 MWIn study Caldwell, TXERCOT Dec 2025target 2027
Texas Sun Solar
Solar · Pigg Grounds LLC
71.7 MWIn study Jackson, TXERCOT Sep 2025target 2027
7L Solar SLF
Solar + storage · 7L Solar, LLC
71.6 MWIn study Dimmit, TXERCOT Sep 2025target 2029
Onshore wind project GEN-2025-SR2, Hansford County
Onshore wind
67.2 MWIn study Hansford, TXSPP May 2025target 2028
PRI Solar
Solar · BHER Power Resources, Inc.
63.8 MWIn study Howard, TXERCOT Jul 2025target 2027
Iron Cowboy Storage
Solar + storage · Vaquero II Storage, LLC
63.3 MWIn study San Patricio, TXERCOT Jun 2025target 2028
Borden Dino BESS
Solar + storage · Borden Dino Solar, LLC
60.3 MWIn study Borden, TXERCOT Apr 2025target 2028
Silver Hills Windpower
Onshore wind · Silver Hills Windpower, LLC
54.1 MWIn study Howard, TXERCOT Apr 2025target 2029
Wagon Timber Storage
Solar + storage · Wagon Timber Storage, LLC
53.5 MWIn study Knox, TXERCOT Jan 2025target 2028
Onshore wind project GEN-2026-PR1, Ochiltree County
Onshore wind
52.6 MWIn study Ochiltree, TXSPP Dec 2025target 2030
GPlains Storage
Solar + storage · Gypsum Plains Solar, LLC
51.3 MWIn study Ector, TXERCOT Apr 2025target 2029
Crocus Storage
Solar + storage · Crocus Solar, LLC
51.0 MWIn study Stephens, TXERCOT Jan 2025target 2028
Battery storage project GEN-2024-305, Marion County
Battery storage
50.0 MWIn study Marion, TXSPP Mar 2025target 2029
Dart Energy Storage A1
Battery storage · Dart Energy Storage LLC
50.0 MWIn study Taylor, TXERCOT Feb 2025target 2028
Buck Ranch Storage SLF
Solar + storage · Buck Ranch Solar, LLC
40.8 MWIn study Live Oak, TXERCOT Jan 2025target 2028
Paolo Sole Hamilton Solar
Solar · Viridian Power Development, LLC
40.6 MWIn study Hamilton, TXERCOT May 2025target 2028
Paolo Sole Gustine Solar
Solar · Viridian Power Development, LLC
40.3 MWIn study Comanche, TXERCOT May 2025target 2028
Ashra Solar SLF
Solar + storage · Ashra Solar, LLC
40.3 MWIn study Uvalde, TXERCOT Apr 2025target 2028
Staghorn Gas
Gas · RPC Merchant LLC
10.0 MWAgreement signed Ward, TXERCOT May 2025target 2026
Harlingen #1 BESS 1
Battery storage · Harlingen ESS Assets LLC
10.0 MWAgreement signed Cameron, TXERCOT May 2025target 2026
Mesquite BESS2
Battery storage · Mesquite Clean Energy Center, LLC
10.0 MWAgreement signed Cameron, TXERCOT Mar 2025target 2026
Knapp BESS
Battery storage · Knapp ESS Assets, LLC
10.0 MWAgreement signed Scurry, TXERCOT Mar 2025target 2025
Beck_Road BESS1
Battery storage · Bexar Corrilla LLC
10.0 MWAgreement signed Bexar, TXERCOT Jul 2025target 2026
Meadow Park BESS
Battery storage · Meadow Park ESS Assets, LLC
10.0 MWAgreement signed Tarrant, TXERCOT Jun 2025target 2026
Alamo Street BESS
Battery storage · Alamo Clean Energy Center, LLC
10.0 MWAgreement signed Pecos, TXERCOT Apr 2025target 2026
Berry BESS1
Battery storage · ESTX-PLD-HOUSTON8, LLC
10.0 MWAgreement signed Harris, TXERCOT Feb 2025target 2025
North Edinburg BESS 1
Battery storage · Edinburg ESS Assets LLC
10.0 MWAgreement signed Hidalgo, TXERCOT May 2025target 2026
Roadrunner Crossing Wind (Uprate)
Wind + storage · Roadrunner Wind, LLC
3.3 MWIn study Eastland, TXERCOT Dec 2025target 2026
Ashra Storage SLF
Solar + storage · Ashra Solar, LLC
1.6 MWIn study Uvalde, TXERCOT Apr 2025target 2028
Kickstart Energy Storage IV
Battery storage · Kickstart Infrastructure LLC
1.4 MWIn study Ellis, TXERCOT Mar 2025target 2029
Kickstart Energy Storage III
Battery storage · Kickstart Infrastructure LLC
1.4 MWIn study Ellis, TXERCOT Mar 2025target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)