🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

WIND + STORAGE · ERCOT

Roadrunner Crossing Wind (Uprate)

Roadrunner Crossing Wind (Uprate) is a 3.3 MW wind + storage request in interconnection study in the ERCOT interconnection queue, in Eastland County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0726
Grid region
ERCOT (Texas)
Developer
Roadrunner Wind, LLC
Connection point (POI)
68051 Reata 345kV
Location
Eastland County, Texas
Technology
Wind: 3.3 MW · Battery
Total requested
3.3 MW
Study phase
SS Started, FIS Started, No IA
Queue status
Active
Entered queue
23 December 2025
Proposed online date
June 2026

Location

Marker shows the centre of Eastland County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Eastland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem