Diamond Sage BESS 2

Diamond Sage BESS 2 is a 100 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Webb County, Texas.

Queue statusIn planning
  1. PlanningQueued Jan 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0444
Grid region
ERCOT (Texas)
Developer
DGC Renewables, LLC
Connection point (POI)
Tap 345kV LOBO7A (80219) - FOWLERTONSW5 (5709)
Location
Webb County, Texas
Technology
Battery: 100 MW · Battery
Total requested
100 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
28 January 2025
Proposed online date
October 2028

Location

Marker shows the centre of Webb County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Webb County