SOLAR + STORAGE · ERCOT

7L Solar SLF

7L Solar SLF is a 71.6 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Dimmit County, Texas.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
29INR0107
Grid region
ERCOT (Texas)
Developer
7L Solar, LLC
Connection point (POI)
Tap 69kV 5870 Brundage - 5868 Big Wells
Location
Dimmit County, Texas
Technology
Solar: 71.6 MW · Battery
Total requested
71.6 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
22 September 2025
Proposed online date
November 2029

Location

Marker shows the centre of Dimmit County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Dimmit County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem