SOLAR + STORAGE · ERCOTCrocus Storage
Crocus Storage is a 51.0 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Stephens County, Texas.
Queue statusIn planning
- PlanningQueued Jan 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0601
- Grid region
- ERCOT (Texas)
- Developer
- Crocus Solar, LLC
- Connection point (POI)
- Tap 138 kV Gunsolas Creek Sub (1660) – Breckenridge Tap (1613)
- Location
- Stephens County, Texas
- Technology
- Battery: 51.0 MW · Battery
- Total requested
- 51.0 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 28 January 2025
- Proposed online date
- July 2028
Location
Marker shows the centre of Stephens County; the queue data does not give exact sites.
Other requests in Stephens County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem