Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown692152.4 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

692 requests · page 8 of 14
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2024-187, Mcclain County
Battery storage
199 MWIn study Mcclain, OKSPP Mar 2025target 2029
Wind + storage project GEN-2024-308, Woodward County
Wind + storage
199 MWIn study Woodward, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-250, Pittsburg County
Battery storage
199 MWIn study Pittsburg, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-320, Wyandotte County
Battery storage
199 MWIn study Wyandotte, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-184, Atoka County
Battery storage
199 MWIn study Atoka, OKSPP Mar 2025target 2029
Solar + storage project GEN-2024-272, Pratt County
Solar + storage
199 MWIn study Pratt, KSSPP Mar 2025target 2029
Battery storage project GEN-2024-167, Ray County
Battery storage
199 MWIn study Ray, MOSPP Mar 2025target 2030
Battery storage project GEN-2024-178, Harrison County
Battery storage
199 MWIn study Harrison, TXSPP Mar 2025target 2029
Battery storage project GEN-2024-318, Tulsa County
Battery storage
199 MWIn study Tulsa, OKSPP Mar 2025target 2028
Solar + storage project GEN-2024-218, Seward County
Solar + storage
199 MWIn study Seward, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-119, Cleveland County
Battery storage
199 MWIn study Cleveland, OKSPP Mar 2025target 2028
Solar + storage project GEN-2024-351, Lea County
Solar + storage
199 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-319, Wyandotte County
Battery storage
199 MWIn study Wyandotte, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-181, Greene County
Battery storage
199 MWIn study Greene, MOSPP Mar 2025target 2029
Battery storage project GEN-2024-245, Lincoln County
Battery storage
199 MWIn study Lincoln, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-121, Leavenworth County
Battery storage
199 MWIn study Leavenworth, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-186, Chaves County
Battery storage
199 MWIn study Chaves, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-118, Wagoner County
Battery storage
199 MWIn study Wagoner, OKSPP Mar 2025target 2028
Onshore wind project GEN-2018-089, Castro County
Onshore wind
196 MWAgreement signed Castro, TXSPP Nov 2018target 2028
Solar project GEN-2024-GR3, Lea County
Solar
196 MWIn study Lea, NMSPP Jun 2024target 2027
Onshore wind project GEN-2024-089, Curry County
Onshore wind
195 MWIn study Curry, NMSPP Oct 2024target 2029
Solar + storage project GEN-2024-267, Bryan County
Solar + storage
195 MWIn study Bryan, OKSPP Mar 2025target 2029
Solar project GEN-2023-210, Lincoln County
Solar
191 MWIn study Lincoln, OKSPP Oct 2023target 2026
Solar project GEN-2024-158, Jackson County
Solar
190 MWIn study Jackson, OKSPP Mar 2025target 2029
Solar project GEN-2017-018, Barber County
Solar
189 MWAgreement signed Barber, KSSPP May 20172025
Onshore wind project GEN-2016-133, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-134, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-138, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-137, Texas County
Onshore wind
188 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Gas project ERAS-2025-003, Oklahoma County
Gas
186 MWIn study Oklahoma, OKSPP Sep 20252025
Battery storage project GEN-2025-SR14, Oklahoma County
Battery storage
183 MWIn study Oklahoma, OKSPP May 2025target 2030
Solar project GEN-2021-108, Cass County
Solar
182 MWIn study Cass, NESPP May 20212025
Solar project GEN-2023-205, Hughes County
Solar
180 MWIn study Hughes, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-136, Bryan County
Battery storage
180 MWIn study Bryan, OKSPP Feb 2023target 2030
Onshore wind project GEN-2017-119, Cloud County
Onshore wind
180 MWAgreement signed Cloud, KSSPP Nov 2017target 2027
Solar project GEN-2022-038, Harrison County
Solar
180 MWIn study Harrison, TXSPP Jun 2022target 2029
Battery storage project GEN-2019-065, Smith County
Battery storage
180 MWIn study Smith, TXSPP May 2019target 2026
Battery storage project GEN-2022-145, Johnston County
Battery storage
180 MWIn study Johnston, OKSPP Feb 2023target 2030
Onshore wind project GEN-2017-222, Crawford County
Onshore wind
180 MWAgreement signed Crawford, IASPP Nov 2017target 2027
Battery storage project GEN-2024-SR5, Creek County
Battery storage
177 MWAgreement signed Creek, OKSPP Feb 2024target 2026
Onshore wind project GEN-2016-128, Alfalfa County
Onshore wind
176 MWAgreement signed Alfalfa, OKSPP Nov 2016target 2026
Solar project GEN-2024-274, Harper County
Solar
175 MWIn study Harper, KSSPP Mar 2025target 2030
Solar project GEN-2022-075, Ellis County
Solar
175 MWIn study Ellis, KSSPP Sep 2022target 2027
Solar project GEN-2024-055, Vernon County
Solar
175 MWIn study Vernon, MOSPP Oct 2024target 2029
Onshore wind project GEN-2011-019, Woodward County
Onshore wind
175 MWAgreement signed Woodward, OKSPP Mar 2011target 2027
Onshore wind project GEN-2016-146, Texas County
Onshore wind
175 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project GEN-2016-145, Texas County
Onshore wind
175 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Solar project ERAS-2025-025, Caddo County
Solar
175 MWIn study Caddo, OKSPP Oct 2025target 2027
Solar + storage project GEN-2023-193, Harrison County
Solar + storage
175 MWIn study Harrison, TXSPP Oct 2023target 2028
Battery storage project GEN-2024-034, Sargent County
Battery storage
175 MWIn study Sargent, NDSPP Oct 2024target 2029
Page 8 of 14

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)