United States › Grid › Interconnection queues › New Mexico

SOLAR · SPP

Solar project GEN-2024-GR3, Lea County

Solar project GEN-2024-GR3, Lea County is a 196 MW solar request in interconnection study in the SPP interconnection queue, in Lea County, New Mexico, connecting to Xcel/SPS.

Queue statusIn planning
  1. PlanningQueued Jun 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-GR3
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
Xcel/SPS
Connection point (POI)
230kV Cunningham Substation
Location
Lea County, New Mexico
Technology
Solar: 196 MW
Total requested
196 MW
Service type
Energy only (ERIS)
Study phase
IA PENDING
Queue status
Active
Entered queue
7 June 2024
Proposed online date
April 2027

Location

Marker shows the centre of Lea County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Lea County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem