Requests shown1,283285.2 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,283 requests ยท page 6 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Willard Storage
Battery storage ยท Emeren US, LLC
300 MWIn study Rensselaer, NYNYISO Sep 2024target 2028
Solar project J3412, Ford County
Solar
300 MWIn study Ford, ILMISO Mar 2024target 2028
Battery storage project J3558, Champaign County
Battery storage
300 MWIn study Champaign, ILMISO Apr 2024target 2027
Battery storage project GEN-2024-SR15, Yoakum County
Battery storage
300 MWIn study Yoakum, TXSPP Oct 2024target 2026
Other project Q570, Yuma County
Other
300 MWIn study Yuma, AZWest May 2024target 2028
Swiss Valley Energy Storage
Battery storage ยท Sawhall Energy Storage LLC
300 MWIn study Wyoming, NYNYISO Oct 2024target 2029
Battery storage project J3525, Rock Island County
Battery storage
300 MWIn study Rock Island, ILMISO Apr 2024target 2028
Onshore wind project GEN-2024-016, Smith County
Onshore wind
300 MWIn study Smith, KSSPP Oct 2024target 2028
Onshore wind project J3384, Big Stone County
Onshore wind
300 MWIn study Big Stone, MNMISO Apr 2024target 2028
Mandolin Solar SLF
Solar + storage ยท Mandolin Solar Project, LLC
300 MWIn study Starr, TXERCOT Jul 2024target 2029
Onshore wind project J3853, Iroquois County
Onshore wind
300 MWIn study Iroquois, ILMISO Dec 2024target 2029
Wind + storage project CS24-15, Lincoln County
Wind + storage
300 MWAgreement signed Lincoln, WAWest Apr 2024target 2029
Solar project GEN-2024-077, Hutchinson County
Solar
300 MWIn study Hutchinson, TXSPP Oct 2024target 2029
Battery storage project J3834, Gibson County
Battery storage
300 MWIn study Gibson, INMISO Sep 2024target 2026
Solar + storage project Q2402, Maricopa County
Solar + storage
300 MWIn study Maricopa, AZWest Feb 2024target 2027
Solar project J3758, Macon County
Solar
300 MWIn study Macon, MOMISO Apr 2024target 2028
Solar project GEN-2024-068, Morris County
Solar
300 MWIn study Morris, TXSPP Oct 2024target 2028
Onshore wind project J3672, Big Stone County
Onshore wind
300 MWIn study Big Stone, MNMISO Apr 2024target 2028
Onshore wind project GEN-2024-GR6, Kay County
Onshore wind
300 MWIn study Kay, OKSPP Jul 2024target 2027
Solar project J3669, Stevens County
Solar
300 MWIn study Stevens, MNMISO Apr 2024target 2028
Battery Storage
Battery storage
300 MWIn study Worcester, MAISO-NE Apr 2024target 2028
Battery storage project Q107, Kern County
Battery storage
300 MWIn study Kern, CAWest May 2024target 2028
Gardner Draw Solar
Solar ยท RWE Clean Energy Development, LLC
300 MWAgreement signed Glasscock, TXERCOT Oct 2024target 2027
Battery storage project J3417, Macon County
Battery storage
300 MWIn study Macon, ILMISO Apr 2024target 2028
Peach Creek Solar
Solar ยท Acciona Energy USA Global LLC
300 MWIn study Wharton, TXERCOT Dec 2024target 2028
Onshore wind project J3280, Dickey County
Onshore wind
300 MWIn study Dickey, NDMISO Apr 2024target 2028
Other project 141, Thurston County
Other
300 MWIn study Thurston, WAWest Feb 2024target 2030
Palo Verde Wind
Wind + storage ยท RWE Clean Energy Development, LLC
298 MWIn study San Patricio, TXERCOT Apr 2024target 2027
Solar project J3282, Mason County
Solar
297 MWIn study Mason, MIMISO Apr 2024target 2028
Sanders Hollow Energy Center
Onshore wind ยท Sanders Hollow Energy Center, LLC
293 MWIn study Dickens, TXERCOT Oct 2024target 2028
Windjammer Windpower
Onshore wind ยท Windjammer Windpower, LLC
293 MWAgreement signed Glasscock, TXERCOT Sep 2024target 2028
Onshore wind project 5RSC-2024-18, Prowers County
Onshore wind
293 MWIn study Prowers, COWest Jan 2024target 2029
Grapefruit Solar
Solar ยท Grapefruit Solar LLC
291 MWAgreement signed Hidalgo, TXERCOT Feb 2024target 2028
Vista Bluff Wind 2
Onshore wind
290 MWPaused / redesign Upton, TXERCOT Sep 2024
Vista Bluff Wind 1
Onshore wind
290 MWPaused / redesign Upton, TXERCOT Sep 2024
Battery Storage
Battery storage
290 MWIn study Berkshire, MAISO-NE Apr 2024target 2028
Solar project J3274, Ogemaw County
Solar
290 MWIn study Ogemaw, MIMISO Apr 2024target 2028
Spindletop Solar
Solar + storage ยท Banita Creek Solar LLC
286 MWAgreement signed Nacogdoches, TXERCOT Jul 2024target 2027
Fierce River BESS
Solar + storage ยท Rio Grande Solar LLC
285 MWIn study Starr, TXERCOT Mar 2024target 2029
Solar + storage project GEN-2024-015, Yoakum County
Solar + storage
280 MWIn study Yoakum, TXSPP Oct 2024target 2028
Unicorn BESS
Battery storage ยท Unicorn Energies
279 MWIn study Fort Bend, TXERCOT Jan 2024target 2027
Gas project 636, Humphreys County
Gas
276 MWIn study Humphreys, TNSoutheast Jul 2024target 2028
Onshore wind project J3564, Newton County
Onshore wind
275 MWIn study Newton, INMISO Apr 2024target 2028
Solar + storage project GEN-2024-035, Brown County
Solar + storage
270 MWIn study Brown, SDSPP Oct 2024target 2027
Solar project J3986, Liberty County
Solar
270 MWIn study Liberty, TXMISO Oct 2024target 2030
Gas project GEN-2024-023, Gage County
Gas
270 MWIn study Gage, NESPP Oct 2024target 2030
Battery storage project IC-1271, Cherokee County
Battery storage
265 MWAgreement signed Cherokee, GASoutheast Mar 2024target 2026
Leopard BESS
Battery storage ยท Bobcat Energy Center, LLC
264 MWAgreement signed Victoria, TXERCOT May 2024target 2028
Onshore wind project J3313, Lenawee County
Onshore wind
263 MWIn study Lenawee, MIMISO Apr 2024target 2028
Verily Solar (FKA Cuello De Cuero Solar)
Solar ยท NextEra Energy Interconnection Holdings, LLC
261 MWIn study Brooks, TXERCOT Mar 2024target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)