Solar project J3669, Stevens County

Solar project J3669, Stevens County is a 300 MW solar request in interconnection study in the MISO interconnection queue, in Stevens County, Minnesota, connecting to OTTER TAIL POWER COMPANY.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3669
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Big Stone South - Alexandria 345.0kV
Location
Stevens County, Minnesota
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
18 April 2024
Proposed online date
February 2028

Location

Marker shows the centre of Stevens County; the queue data does not give exact sites.