ONSHORE WIND Β· MISOOnshore wind project G638, Stevens County
Onshore wind project G638, Stevens County is a 20.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Stevens County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2006 (completed)
- Withdrawn / abandonedNov 2013 (project stopped here)
- ConsentedNov 2013 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G638
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- OTP Graceville - Morris 41 kV
- Location
- Stevens County, Minnesota
- Technology
- Wind: 20.0 MW
- Total requested
- 20.0 MW
- Study phase
- Network Upgrade
- Queue status
- Withdrawn
- Entered queue
- 17 May 2006
- Agreement signed
- 7 November 2013
- Proposed online date
- November 2007
- Withdrawn
- November 2013
Location
Marker shows the centre of Stevens County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Stevens County
- Solar project J3669, Stevens CountySolar Β· 300 MW Β· in study
- Solar project J2608, Stevens CountySolar Β· 160 MW Β· in study
- Battery storage project J2624, Stevens CountyBattery storage Β· 450 MW Β· withdrawn
- Onshore wind project G805, Stevens CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project G737, Stevens CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project G555, Stevens CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project G777, Stevens CountyOnshore wind Β· 20.0 MW Β· withdrawn
- Onshore wind project G644, Stevens CountyOnshore wind Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem