United States › Grid › Interconnection queues › Washington
WIND + STORAGE · WESTWind + storage project CS24-15, Lincoln County
Wind + storage project CS24-15, Lincoln County is a 300 MW wind + storage request with a signed interconnection agreement in the West interconnection queue, in Lincoln County, Washington, connecting to Avista Utilities.
Queue statusConsented
- PlanningQueued Apr 2024 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- CS24-15
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Avista Utilities
- Connection point (POI)
- Bluebird 230kV Station
- Location
- Lincoln County, Washington
- Technology
- Wind: 300 MW · Battery
- Total requested
- 300 MW
- Service type
- NRIS and ERIS
- Study phase
- Request Status: LGIA; Facilities Study: Complete; Phase One Cluster Study: Complete; Phase One Re-Study: N/A; Phase Two
- Queue status
- Active
- Entered queue
- 30 April 2024
- Proposed online date
- December 2029
Location
Marker shows the centre of Lincoln County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Lincoln County
- Solar project CS23-13, Lincoln CountySolar · 40.0 MW · agreement signed
- Onshore wind project G0953, Lincoln CountyOnshore wind · 600 MW · in study
- Onshore wind project G0955, Lincoln CountyOnshore wind · 350 MW · in study
- Onshore wind project G0954, Lincoln CountyOnshore wind · 350 MW · in study
- Solar + storage project G0985, Lincoln CountySolar + storage · 225 MW · in study
- Solar project 103, Lincoln CountySolar · 40.0 MW · in study
- Solar project 71, Lincoln CountySolar · 1.0 MW · in study
- Gas project 41, Lincoln CountyGas · 0.3 MW · in study
- Battery storage project 74, Lincoln CountyBattery storage · 0.1 MW · built
- Onshore wind project G0860, Lincoln CountyOnshore wind · 300 MW · withdrawn
- Solar + storage project 112, Lincoln CountySolar + storage · 190 MW · withdrawn
- Solar + storage project TCS-16, Lincoln CountySolar + storage · 125 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem