🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Washington

SOLAR · WEST

Solar project CS23-13, Lincoln County

Solar project CS23-13, Lincoln County is a 40.0 MW solar request with a signed interconnection agreement in the West interconnection queue, in Lincoln County, Washington, connecting to Avista Utilities.

Queue statusConsented
  1. PlanningQueued May 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
CS23-13
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Davenport 115kV Station
Location
Lincoln County, Washington
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
Request Status: LGIA; Facilities Study: Complete; Phase One Cluster Study: Complete; Phase One Re-Study: Complete; Phase
Queue status
Active
Entered queue
1 May 2023
Proposed online date
June 2028

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem