πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

SOLAR + STORAGE Β· WEST

Solar + storage project 112, Lincoln County

Solar + storage project 112, Lincoln County is a 190 MW solar + storage request withdrawn in the West interconnection queue, in Lincoln County, Washington, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
112
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Irby 115kV substation or Irby to Wilson Creek 115kV line
Location
Lincoln County, Washington
Technology
Solar: 125 MW Β· Battery: 65.0 MW
Total requested
190 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
7 January 2021
Proposed online date
December 2024

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem