🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J3282, Mason County

Solar project J3282, Mason County is a 297 MW solar request in interconnection study in the MISO interconnection queue, in Mason County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3282
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
KEYSTONE - LUDINGTON 345.0kV
Location
Mason County, Michigan
Technology
Solar: 297 MW
Total requested
297 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
15 April 2024
Proposed online date
November 2028

Location

Marker shows the centre of Mason County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Mason County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem