🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

BATTERY STORAGE · MISO

Battery storage project J2392, Mason County

Battery storage project J2392, Mason County is a 100 MW battery storage request in interconnection study in the MISO interconnection queue, in Mason County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2392
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
PERE MARQUETTE 138 KV
Location
Mason County, Michigan
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
15 September 2022
Proposed online date
October 2026

Location

Marker shows the centre of Mason County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Mason County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem