Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown281108.6 GW
Active in queue108.6 GW281 requests
Agreement signed9,849 MW17 requests
Withdrawn699198.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

281 requests · page 5 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project Q422, Navajo County
Battery storage
200 MWIn study Navajo, AZWest Sep 2021target 2025
Solar + storage project Q442, Yuma County
Solar + storage
200 MWIn study Yuma, AZWest Mar 2022target 2026
Other project 109, Pima County
Other · TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Battery storage project 121, Pinal County
Battery storage
200 MWIn study Pinal, AZWest May 2022target 2026
Other project 77, Apache County
Other
200 MWIn study Apache, AZWest Feb 2020target 2023
Gas project 2024-G2, Mohave County
Gas
200 MWIn study Mohave, AZWest Feb 2024target 2027
Battery storage project 143, Pima County
Battery storage
200 MWIn study Pima, AZWest Nov 2022target 2025
Other project 108, Pima County
Other · TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Solar + storage project 2023-G10, Pinal County
Solar + storage
200 MWIn study Pinal, AZWest Jul 2023target 2027
Other project Q573, Pinal County
Other
200 MWIn study Pinal, AZWest May 2024target 2028
Solar + storage project Q333, Navajo County
Solar + storage
200 MWIn study Navajo, AZWest Mar 2020target 2024
Solar + storage project SP111, Pinal County
Solar + storage
192 MWIn study Pinal, AZWest target 2026
Other project Q590, Maricopa County
Other
180 MWIn study Maricopa, AZWest May 2025target 2028
Battery storage project 146, Pima County
Battery storage
175 MWIn study Pima, AZWest Dec 2022target 2026
Battery storage project Q479, Maricopa County
Battery storage
165 MWIn study Maricopa, AZWest Sep 2022target 2028
Other project Q565, Coconino County
Other
161 MWIn study Coconino, AZWest May 2024target 2025
Other project Q612, Coconino County
Other
161 MWIn study Coconino, AZWest May 2025target 2028
Battery storage project Q2503, Maricopa County
Battery storage
155 MWIn study Maricopa, AZWest Feb 2025target 2029
Solar + storage project 2022-G11, Maricopa County
Solar + storage
150 MWIn study Maricopa, AZWest Aug 2022target 2025
Battery storage project 147, Pima County
Battery storage
150 MWIn study Pima, AZWest Dec 2022target 2026
Solar + storage project 2022-G10, Pinal County
Solar + storage
150 MWIn study Pinal, AZWest Jul 2022target 2025
Battery storage project Q357, Maricopa County
Battery storage
150 MWUnder construction Maricopa, AZWest Sep 2020target 2023
Solar + storage project Q463, Maricopa County
Solar + storage
150 MWIn study Maricopa, AZWest Mar 2022target 2024
Battery storage project Q299, Maricopa County
Battery storage
150 MWAgreement signed Maricopa, AZWest Mar 2019target 2023
Battery storage project 122, Pinal County
Battery storage
150 MWIn study Pinal, AZWest May 2022target 2026
Solar + storage project 2023-G6, Mohave County
Solar + storage
150 MWIn study Mohave, AZWest May 2023target 2027
Battery storage project 132, Pima County
Battery storage
150 MWIn study Pima, AZWest Jul 2022target 2025
Other project Q587, Pinal County
Other
150 MWIn study Pinal, AZWest May 2025target 2031
Other project Q548, Pinal County
Other
145 MWIn study Pinal, AZWest Apr 2024target 2027
Onshore wind project 2021-G6, Yavapai County
Onshore wind
135 MWIn study Yavapai, AZWest Jun 2021target 2025
Solar + storage project Q264, Pinal County
Solar + storage
130 MWAgreement signed Pinal, AZWest Sep 2017target 2021
Gas project Q37, Maricopa County
Gas
130 MWIn study Maricopa, AZWest Feb 2023target 2024
Other project Q588, Pinal County
Other
130 MWIn study Pinal, AZWest May 2025target 2031
Other project Q614, Maricopa County
Other
125 MWIn study Maricopa, AZWest May 2025target 2027
Saddle Mountain Solar
Solar
125 MWAgreement signed Maricopa, AZCAISO Apr 2020target 2025
Battery storage project Q423, Navajo County
Battery storage
125 MWIn study Navajo, AZWest Sep 2021target 2025
Battery storage project Q384, Maricopa County
Battery storage
125 MWPaused / redesign Maricopa, AZWest Mar 2021target 2025
Solar + storage project 2021-G3, Pinal County
Solar + storage
119 MWIn study Pinal, AZWest Apr 2021target 2023
Solar + storage project 165, Pima County
Solar + storage
100 MWIn study Pima, AZWest Sep 2023target 2028
Battery storage project Q358, Maricopa County
Battery storage
100 MWAgreement signed Maricopa, AZWest Sep 2020target 2024
Solar + storage project Q579, Pinal County
Solar + storage
100 MWIn study Pinal, AZWest Apr 2025target 2029
Solar + storage project Q493, Pinal County
Solar + storage
100 MWIn study Pinal, AZWest Feb 2023target 2025
Other project 115, Pima County
Other
100 MWIn study Pima, AZWest Mar 2022target 2025
Other project 116, Pima County
Other
100 MWIn study Pima, AZWest Mar 2022target 2025
Solar project Q254, Pinal County
Solar
100 MWAgreement signed Pinal, AZWest Mar 2017target 2022
Battery storage project Q372, Maricopa County
Battery storage
100 MWIn study Maricopa, AZWest Mar 2021target 2024
Solar + storage project Q256, Pinal County
Solar + storage
100 MWIn study Pinal, AZWest May 2017target 2023
Battery storage project Q363, Maricopa County
Battery storage
100 MWIn study Maricopa, AZWest Sep 2020target 2023
Solar + storage project Q313, Yavapai County
Solar + storage
95.0 MWIn study Yavapai, AZWest Sep 2019target 2022
Battery storage project Q297, Yuma County
Battery storage
90.1 MWIn study Yuma, AZWest Mar 2019target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)