United States › Grid › Interconnection queues › Arizona

SOLAR + STORAGE · WEST

Solar + storage project Q256, Pinal County

Solar + storage project Q256, Pinal County is a 100 MW solar + storage request in interconnection study in the West interconnection queue, in Pinal County, Arizona, connecting to Arizona Public Service.

Queue statusIn planning
  1. PlanningQueued May 2017 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q256
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Milligan 69kV Substation
Location
Pinal County, Arizona
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Project with APS Project Manager
Queue status
Active
Entered queue
24 May 2017
Proposed online date
January 2023

Location

Marker shows the centre of Pinal County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Pinal County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem