🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Arizona

SOLAR + STORAGE · WEST

Solar + storage project Q264, Pinal County

Solar + storage project Q264, Pinal County is a 130 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Pinal County, Arizona, connecting to Arizona Public Service.

Queue statusConsented
  1. PlanningQueued Sep 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2021 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
Q264
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Milligan Substation 230kV
Location
Pinal County, Arizona
Technology
Solar: 130 MW · Battery
Total requested
130 MW
Service type
Network resource (NRIS)
Study phase
In Design
Queue status
Active
Entered queue
29 September 2017
Proposed online date
December 2021

Location

Marker shows the centre of Pinal County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Pinal County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem