United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2019 requests) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,473226.5 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,473 requests · page 4 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Hale 1
Onshore wind · NextEra Energy
322 MWWithdrawn / abandoned Hale, TXERCOT Apr 2019target 2020
Solar + storage project 1109, Sweetwater County
Solar + storage
320 MWWithdrawn / abandoned Sweetwater, WYWest Jan 2019target 2023
Solar + storage project 1106, Sweetwater County
Solar + storage
320 MWWithdrawn / abandoned Sweetwater, WYWest Jan 2019target 2023
Solar + storage project 1108, Sweetwater County
Solar + storage
320 MWWithdrawn / abandoned Sweetwater, WYWest Jan 2019target 2023
Solar + storage project 1110, Sweetwater County
Solar + storage
320 MWWithdrawn / abandoned Sweetwater, WYWest Jan 2019target 2028
Solar project AE2-313, Dinwiddie County
Solar · RWE Solar Development, LLC
314 MWWithdrawn / abandoned Dinwiddie, VAPJM Mar 2019target 2022
Onshore wind project G0611, Klickitat County
Onshore wind
313 MWWithdrawn / abandoned Klickitat, WAWest Jan 2019target 2021
Barrenspring
Solar + storage
308 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Vestal Valley
Solar + storage
308 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
San Bernardino BESS
Battery storage
308 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2019target 2022
Hinson BESS
Battery storage
308 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Nikola Norte
Solar + storage
306 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2019target 2023
Tesoster
Solar + storage
306 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2019target 2023
Nikovaster
Solar + storage
306 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2019target 2023
Superba Storage 1
Battery storage
305 MWWithdrawn / abandoned Orange, CACAISO Apr 2019target 2021
Frio Flat Wind
Onshore wind · Phoenix Wind, LLC
305 MWWithdrawn / abandoned Deaf Smith, TXERCOT Jun 2019target 2022
Arcturus
Solar + storage
304 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2026
Voyager Solar
Solar · EDF Renewables Development, Inc.
304 MWWithdrawn / abandoned Wharton, TXERCOT Jan 2019target 2025
Onshore wind project AF2-003, Marshall County
Onshore wind
303 MWWithdrawn / abandoned Marshall, ILPJM Oct 2019target 2023
Sugarloaf Hybrid Solar
Solar + storage
303 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Solar project GEN-2019-031, Lea County
Solar
303 MWWithdrawn / abandoned Lea, NMSPP Apr 2019target 2021
Offshore wind project AE2-222, Atlantic County
Offshore wind
300 MWWithdrawn / abandoned Atlantic, NJPJM Mar 2019target 2023
CWW 300 MW Dun
Onshore wind · Diamond Generating Corporation
300 MWWithdrawn / abandoned Chautauqua, NYNYISO Apr 2019
Yacht Club Energy Storage
Battery storage · sPower Development Company, LLC
300 MWWithdrawn / abandoned New York, NYNYISO Aug 2019
Onshore wind project MPC04100, Grand Forks County
Onshore wind
300 MWWithdrawn / abandoned Grand Forks, NDMISO Apr 2019target 2023
Solar + storage project Q69, San Bernardino County
Solar + storage
300 MWWithdrawn / abandoned San Bernardino, CAWest Apr 2019target 2022
Onshore wind project J1456, Sheridan County
Onshore wind
300 MWWithdrawn / abandoned Sheridan, NDMISO Apr 2019target 2023
Solar + storage project Company 188, Clark County
Solar + storage
300 MWWithdrawn / abandoned Clark, NVWest Sep 2019target 2022
CWW 300 Wind
Onshore wind · Diamond Generating Corporation
300 MWWithdrawn / abandoned Erie, NYNYISO Apr 2019
Solar + storage project 1171, Converse County
Solar + storage
300 MWWithdrawn / abandoned Converse, WYWest Oct 2019target 2021
Solar project GEN-2019-008, Chaves County
Solar
300 MWWithdrawn / abandoned Chaves, NMSPP Apr 2019target 2022
Taproot Solar Energy Energy
Solar · Invenergy Solar Project Development LLC
300 MWWithdrawn / abandoned Montgomery, NYNYISO Jun 2019
Chelsea Energy Storage Center
Battery storage · sPower Development Company, LLC
300 MWWithdrawn / abandoned New York, NYNYISO May 2019
Lazarus Solar
Solar · Lendlease Energy Development
300 MWWithdrawn / abandoned Swisher, TXERCOT Dec 2019target 2022
Rescue Energy Storage Center
Battery storage · sPower Development Company, LLC
300 MWWithdrawn / abandoned New York, NYNYISO May 2019
Goethals Energy Storage
Battery storage · sPower Development Company, LLC
300 MWWithdrawn / abandoned New York, NYNYISO Aug 2019
Onshore wind project 68, Cochise County
Onshore wind
300 MWWithdrawn / abandoned Cochise, AZWest Apr 2019target 2022
Solar + storage project Company JU, Eureka County
Solar + storage
300 MWWithdrawn / abandoned Eureka, NVWest Mar 2019target 2023
Plateau Solar
Solar · Innovative Solar 206, LLC
300 MWWithdrawn / abandoned ERCOT Dec 2019target 2025
Solar project G0630, Deer Lodge County
Solar
300 MWWithdrawn / abandoned Deer Lodge, MTWest Oct 2019target 2022
Lazy J Solar
Solar · ConnectGen Operating LLC
300 MWWithdrawn / abandoned Leon, TXERCOT Jul 2019target 2021
Solar project 572, Jerome County
Solar
300 MWWithdrawn / abandoned Jerome, IDWest Nov 2019
MykawaAlta
Gas · Alta Power LLC
300 MWWithdrawn / abandoned Harris, TXERCOT Aug 2019target 2021
Solar + storage project Company KE, Churchill County
Solar + storage
300 MWWithdrawn / abandoned Churchill, NVWest Sep 2019target 2022
Solar project G0632, Grant County
Solar
300 MWWithdrawn / abandoned Grant, WAWest Nov 2019target 2022
Saturn 1 Wind
Onshore wind · Saturn 1 wind
300 MWWithdrawn / abandoned Zapata, TXERCOT Jul 2019target 2022
Welder Solar
Solar · Welder Solar, LLC
300 MWWithdrawn / abandoned Bee, TXERCOT Jun 2019target 2024
Solar project J1413, Howard County
Solar
300 MWWithdrawn / abandoned Howard, IAMISO Apr 2019target 2022
Birch Solar
Solar
300 MWWithdrawn / abandoned Allen, OHPJM Sep 2019target 2027
Solar project J1337, Sherburne County
Solar
300 MWWithdrawn / abandoned Sherburne, MNMISO Apr 2019target 2022
Page 4 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)