United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

SOLAR Β· SPP

Solar project GEN-2019-008, Chaves County

Solar project GEN-2019-008, Chaves County is a 300 MW solar request withdrawn in the SPP interconnection queue, in Chaves County, New Mexico, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedNov 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2019-008
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Eddy - Chaves 230kV transmission line
Location
Chaves County, New Mexico
Technology
Solar: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
23 April 2019
Proposed online date
December 2022
Withdrawn
November 2019

Location

Marker shows the centre of Chaves County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in Chaves County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem