United States › Grid › Interconnection queues › Iowa
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Iowa — page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project J2435, Webster County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J447, Cerro Gordo County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J1467, Fayette County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J2106, Story County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J3250, Cerro Gordo County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project GI-0320, O'brien County Onshore wind · Highland Wind Energy L |
150 MW | Withdrawn / abandoned |
| Onshore wind project R56, Audubon County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project G790, Franklin County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J959, Fayette County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J2079, Hancock County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J114, Tama County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project GI-0407, O'brien County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project G716, Howard County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J840, Humboldt County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J297, O'brien County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J2040, Dickinson County Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar project J990, Dubuque County Solar |
150 MW | Withdrawn / abandoned |
| Onshore wind project G740, Howard County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project R66, Adams County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J2256, Humboldt County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J563, Marshall County Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar project J2108, Johnson County Solar |
150 MW | Withdrawn / abandoned |
| Solar project J3921, Jasper County Solar |
150 MW | Withdrawn / abandoned |
| Solar project J1416, Worth County Solar |
149 MW | Withdrawn / abandoned |
| Onshore wind project R67, Clay County Onshore wind |
149 MW | Withdrawn / abandoned |
| Gas project J810, Audubon County Gas |
146 MW | Withdrawn / abandoned |
| Onshore wind project J2323, Webster County Onshore wind |
145 MW | Withdrawn / abandoned |
| Onshore wind project GI-0813a, Kossuth County Onshore wind |
145 MW | Withdrawn / abandoned |
| Onshore wind project J1176, Cerro Gordo County Onshore wind |
145 MW | Withdrawn / abandoned |
| Onshore wind project J1903, Osceola County Onshore wind |
140 MW | Withdrawn / abandoned |
| Onshore wind project J3325, Cherokee County Onshore wind |
140 MW | Withdrawn / abandoned |
| Onshore wind project J3527, Allamakee County Onshore wind |
136 MW | Withdrawn / abandoned |
| Coal project J357, Woodbury County Coal |
135 MW | Withdrawn / abandoned |
| Solar project J3148, Greene County Solar |
131 MW | Withdrawn / abandoned |
| Onshore wind project J2466, Howard County Onshore wind |
130 MW | Withdrawn / abandoned |
| Onshore wind project GI-0305, Sioux County Onshore wind |
126 MW | Withdrawn / abandoned |
| Other project G318, Sioux County Other |
125 MW | Withdrawn / abandoned |
| Solar project J1549, Clinton County Solar |
125 MW | Withdrawn / abandoned |
| Onshore wind project H097, Boone County Onshore wind |
121 MW | Withdrawn / abandoned |
| Gas project GI-0617, Crawford County Gas |
120 MW | Withdrawn / abandoned |
| Onshore wind project J562, Marshall County Onshore wind |
120 MW | Withdrawn / abandoned |
| Other project G104, Winnebago County Other |
118 MW | Withdrawn / abandoned |
| Onshore wind project J2352, Woodbury County Onshore wind |
118 MW | Withdrawn / abandoned |
| Gas project J360, Scott County Gas |
116 MW | Withdrawn / abandoned |
| Gas project J361, Pottawattamie County Gas |
116 MW | Withdrawn / abandoned |
| Gas project J362, Polk County Gas |
116 MW | Withdrawn / abandoned |
| Solar project J1972, Des Moines County Solar |
115 MW | Withdrawn / abandoned |
| Onshore wind project G702, Worth County Onshore wind |
110 MW | Withdrawn / abandoned |
| Onshore wind project G499, Story County Onshore wind |
110 MW | Withdrawn / abandoned |
| Onshore wind project J029, Howard County Onshore wind |
102 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)277 · 61.2 GW
- PJM (Mid-Atlantic, Midwest)2 · 3,000 MW
- West (non-ISO utilities)15 · 1,796 MW
- SPP (Southwest Power Pool)1 · 74.0 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)