United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project J2256, Humboldt County
Onshore wind project J2256, Humboldt County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Humboldt County, Iowa, connecting to MIDAMERICAN ENERGY CO..
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedSep 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2256
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MIDAMERICAN ENERGY CO.
- Connection point (POI)
- Irvington - Webster 345kV Line
- Location
- Humboldt County, Iowa
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 3
- Queue status
- Withdrawn
- Entered queue
- 16 August 2021
- Proposed online date
- September 2024
- Withdrawn
- September 2021
Location
Marker shows the centre of Humboldt County; the queue data does not give exact sites.
Other requests in Humboldt County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem