ONSHORE WIND · MISOOnshore wind project J2988, Humboldt County
Onshore wind project J2988, Humboldt County is a 175 MW onshore wind request in interconnection study in the MISO interconnection queue, in Humboldt County, Iowa, connecting to MIDAMERICAN ENERGY CO..
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2988
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MIDAMERICAN ENERGY CO.
- Connection point (POI)
- J2256 POI - Irvington 345kV line
- Location
- Humboldt County, Iowa
- Technology
- Wind: 175 MW
- Total requested
- 175 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 September 2022
- Proposed online date
- March 2025
Location
Marker shows the centre of Humboldt County; the queue data does not give exact sites.
Other requests in Humboldt County