United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· WESTOnshore wind project GI-0305, Sioux County
Onshore wind project GI-0305, Sioux County is a 126 MW onshore wind request withdrawn in the West interconnection queue, in Sioux County, Iowa, connecting to WAPA/BEPC/HCPD Integrated System.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2003 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-0305
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA/BEPC/HCPD Integrated System
- Connection point (POI)
- Lebanon
- Location
- Sioux County, Iowa
- Technology
- Wind: 126 MW
- Total requested
- 126 MW
- Study phase
- IAP
- Queue status
- Withdrawn
- Entered queue
- 7 April 2003
Location
Marker shows the centre of Sioux County; the queue data does not give exact sites.
Other requests in Sioux County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem