United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project J1903, Osceola County
Onshore wind project J1903, Osceola County is a 140 MW onshore wind request withdrawn in the MISO interconnection queue, in Osceola County, Iowa, connecting to ITC MIDWEST.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1903
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Osceola (43.431167, -95.416667)
- Location
- Osceola County, Iowa
- Technology
- Wind: 140 MW
- Total requested
- 140 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 3; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 3 August 2021
- Proposed online date
- October 2024
- Withdrawn
- October 2025
Location
Marker shows the centre of Osceola County; the queue data does not give exact sites.
Other requests in Osceola County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem