United States › Grid › Interconnection queues › Iowa

ONSHORE WIND · MISO

Onshore wind project G301, Osceola County

Onshore wind project G301, Osceola County is a 4.0 MW onshore wind request built and operating in the MISO interconnection queue, in Osceola County, Iowa.

Queue statusOperating
  1. PlanningQueued Feb 2003 (completed)
  2. ConsentedNov 2003 (completed)
  3. Construction (completed)
  4. OperatingSep 2003 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G301
Grid region
MISO (Midcontinent)
Connection point (POI)
Sibley - Triboji 69kV
Location
Osceola County, Iowa
Technology
Wind: 4.0 MW
Total requested
4.0 MW
Study phase
SPA - SIS
Queue status
Operational
Entered queue
24 February 2003
Agreement signed
14 November 2003
Proposed online date
September 2003
Came online
September 2003

Location

Marker shows the centre of Osceola County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Osceola County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem