United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project H097, Boone County
Onshore wind project H097, Boone County is a 121 MW onshore wind request withdrawn in the MISO interconnection queue, in Boone County, Iowa.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2008 (completed)
- Withdrawn / abandonedDec 2011 (project stopped here)
- ConsentedDec 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- H097
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- NE Ankeny - Perry 161kV
- Location
- Boone County, Iowa
- Technology
- Wind: 121 MW
- Total requested
- 121 MW
- Study phase
- Optional
- Queue status
- Withdrawn
- Entered queue
- 4 August 2008
- Agreement signed
- 1 December 2011
- Proposed online date
- December 2011
- Withdrawn
- December 2011
Location
Marker shows the centre of Boone County; the queue data does not give exact sites.
Other requests in Boone County
- Onshore wind project J498, Boone CountyOnshore wind Β· 340 MW Β· built
- Onshore wind project J1050, Boone CountyOnshore wind Β· 225 MW Β· built
- Onshore wind project J691, Boone CountyOnshore wind Β· 160 MW Β· withdrawn
- Onshore wind project G813, Boone CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project J3555, Boone CountyOnshore wind Β· 84.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem