πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J029, Howard County

Onshore wind project J029, Howard County is a 102 MW onshore wind request withdrawn in the MISO interconnection queue, in Howard County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2009 (completed)
  2. Withdrawn / abandonedNov 2010 (project stopped here)
  3. ConsentedNov 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J029
Grid region
MISO (Midcontinent)
Connection point (POI)
Adams Substation
Location
Howard County, Iowa
Technology
Wind: 102 MW
Total requested
102 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
11 March 2009
Agreement signed
29 November 2010
Proposed online date
September 2012
Withdrawn
November 2010

Location

Marker shows the centre of Howard County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Howard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem