United States βΊ Grid βΊ Interconnection queues βΊ Iowa
SOLAR Β· MISOSolar project J3921, Jasper County
Solar project J3921, Jasper County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Jasper County, Iowa, connecting to MIDAMERICAN ENERGY CO..
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2025 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3921
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MIDAMERICAN ENERGY CO.
- Connection point (POI)
- BONDURANT - MONTEZUMA 345.0kV
- Location
- Jasper County, Iowa
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 7 March 2025
- Proposed online date
- September 2027
- Withdrawn
- December 2025
Location
Marker shows the centre of Jasper County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem