United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project J297, O'brien County
Onshore wind project J297, O'brien County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in O'brien County, Iowa.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2013 (completed)
- Withdrawn / abandonedJul 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J297
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- on 345kV O'Brien to Webster Line
- Location
- O'brien County, Iowa
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 9 October 2013
- Withdrawn
- July 2015
Location
Marker shows the centre of O'brien County; the queue data does not give exact sites.
Other requests in O'brien County
- Onshore wind project R39, O'brien CountyOnshore wind Β· 500 MW Β· built
- Onshore wind project J285, O'brien CountyOnshore wind Β· 250 MW Β· built
- Onshore wind project J072, O'brien CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GI-0320, O'brien CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project GI-0407, O'brien CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project H040, O'brien CountyOnshore wind Β· 81.0 MW Β· withdrawn
- Other project G316, O'brien CountyOther Β· 80.0 MW Β· withdrawn
- Onshore wind project GI-0304, O'brien CountyOnshore wind Β· 80.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem